How long is net-meter approval valid?
Reviewed by SolvSolar · Last reviewed:
Technical feasibility approval for net metering typically lapses after 3–6 months if the system is not commissioned, and the application must then be refiled from scratch. Build that window into project timelines and avoid filing before equipment procurement is confirmed, since a lapsed approval can push a project back by several weeks.